Upcoming McNab Road Bridge Improvement in Pompano Beach
Upcoming McNab Road Bridge Replacement in Pompano Beach
๐๏ธ Overview of the Bridge Replacement Project
The City of Pompano Beach is moving forward with the long-awaited replacement of the McNab Road Bridge over the C-14 canal. The Florida Department of Transportation (FDOT) officially classified the existing bridge as functionally obsolete following an inspection on March 31, 2024, prompting the need for major improvements.
๐ Project Timeline and Construction Phases
The bridge project will be completed in two major phases:
Phase 1: Streetscape Enhancements
Start Date: May/June 2025
Estimated Completion: November 2026
Focused on beautifying and upgrading the surrounding streets and infrastructure.
Phase 2: Bridge Replacement
Start Date: May 2026
Estimated Completion: September 2026
This phase will involve the complete demolition and rebuilding of the McNab Road Bridge.
๐ Traffic Alert: The bridge will be closed to automobile traffic during construction. Although a temporary bridge was once proposed, it was ultimately ruled out due to feasibility concerns. Residents can expect increased vehicle flow through nearby neighborhoods, particularly between McNab Road and NE 62nd Street.
๐ Improvements for Waterfront Property Owners
Residents of Imperial Point and nearby communities with waterfront homes will benefit from the increased bridge clearance. The new structure will provide an additional 4 feet of vertical clearance, allowing:
Wider tide windows for navigating in and out
Larger boats and watercrafts to pass more freely
This change has seen several revisions but is now confirmed in the final plans.
๐ Updated Navigational Clearances
| Clearance Type | Current Bridge | Proposed Bridge |
|---|---|---|
| Horizontal | 29.75 ft (between pile faces) | 38 ft |
| Vertical โ Mean High Water | 6.44 ft | 10.37 ft |
| Vertical โ Mean Low Water | 8.36 ft | 12.29 ft |